TEYING BUYER GUIDE · UPDATED OCTOBER 23, 2026
A 60-Piece Jewelry Order, Week by Week: Timeline and Fees
Sixty pieces per design is a calendar problem before it is a quantity problem. The stages, the fee credit rules, and two worked cost examples.

Three clocks, not one
A first jewelry order runs on three clocks at once. The development clock covers sketches, CAD and specification. The sampling clock covers the physical piece in your hand. The production clock covers the bulk run after you sign off. Most buyers plan only the third one, then wonder why the launch date slipped.
The numbers at TEYING are 60 pieces per design to start, 300 to 500 pieces as the comfortable production range, sampling in 14 to 18 days, and bulk in 2 to 3 weeks after sample approval. The design and development fee is credited once the production order passes $2,000, and the sample fee comes off the production order. Read those together and the real constraint on a first order is the calendar, not the piece count.
What the number 60 actually covers
Sixty is per design, not per order. Three designs at 60 pieces is a 180-piece order, and each design is reviewed on its own merits.
Four variables decide whether the 60 holds as quoted.
How many finishes. Every plating color is a separate production run. A design ordered in 18K gold and rhodium needs 60 pieces in each finish unless the split is agreed as part of the project. Get the finish split written into the quotation instead of assuming it.
How many designs. Several designs in the same material family can often share a production plan. Three simple brass designs at 60 pieces each are usually easier to schedule than one design in five finishes, even though the piece count is lower.
Stones and pearls. Setting adds a component and a QC step. CZ, pearl and gemstone each carry their own sourcing and matching work, and pearl matching is graded by size and luster rather than counted by weight. Stone and pearl requirements are confirmed per project, because the same 60 pieces can be routine or difficult depending on the material.
Packaging. Logo cards, pouches and boxes have their own print quantities. Treat private-label packaging as a separate workstream with a separate minimum.
Where 60 comes from
Sixty is roughly the point where mold and setup costs stop dominating the unit price of a simple piece. Below it, the tooling is a bigger share of what you pay than the metal is. That is the whole logic, and it is why the number is a starting point rather than a policy.
At 300 to 500 pieces, unit prices step down, plating batches fill more efficiently, and a packaging run starts to make economic sense. It is not a rule or a threshold. It is the range where production economics stop working against the order. A first order at 60 per design is a legitimate order; a reorder at 300 to 500 is where the margin usually appears. The first order buys information. The second one buys margin.
The calendar, stage by stage
| Window | Stage | What gets fixed |
|---|---|---|
| Before day 0 | Brief and quotation | Reference, quantity per design, material, finish, stone or pearl, packaging, target market |
| Running alongside quoting | Design and development | Sketch or CAD reviewed, specification set, $200 to $800 per design |
| Day 1 to 18 | Sample production | Sample built to the approved specification, 14 to 18 days |
| Whenever you are ready | Sample approval | Piece in hand, written approval, one reference sample kept |
| Week 3 onward | Bulk production | Quantity and finish locked, 2 to 3 weeks after approval |
| Inside the bulk window | Packaging and QC | Artwork approved, packing checked against the list |
| At dispatch | Shipping | Quoted by destination, weight and volume |
Factory time from an approved brief to dispatch is roughly four to six weeks when the sample passes first time. A sample revision restarts the clock from the revision date, and that is the single most common reason a first order runs long. Settling the specification before sampling starts costs less than changing it afterwards.
Shipping is quoted by destination, weight and volume rather than published as a rate, across DHL, FedEx, UPS and sea freight. Small runs usually fly; a 500-piece order with packaging often makes more sense by sea.
The fee stack before production
Three charges sit in front of the bulk order. Two of them come back.
| Item | Range | How it is treated |
|---|---|---|
| Design and development | $200 to $800 per design | Credited once the production order passes $2,000 |
| Mold or tooling | $50 to $300 per design, charged once | Mold ownership stays with the client |
| Sample | $50 to $150 per sample | Credited against the production order |
The $2,000 condition attaches to the design and development fee, and it measures the production order rather than total project spend. That distinction is why the 300 to 500 range matters more than it looks.
Two worked examples
First, three designs at mid-range figures across the published bands.
| Line | Amount |
|---|---|
| Design and development, 3 designs at $250 | $750 |
| Molds, 3 designs at $70 | $210 |
| Samples, 3 at $60 | $180 |
| Production: 120 statement earrings with crystal setting at $9.00, plus 60 sterling silver pendants with stone at $18.00 | $2,160 |
| Credit back against the production order, design and development plus samples | -$930 |
| Net project cost | $2,370 |
The design and development credit applies because the production order sits above $2,000.
Now the same arithmetic at the floor. Sixty plain gold-plated brass rings at $2.50 each is a $150 production order. The order is real, the mold is real, and the credits do not apply, because there is no production value for them to attach to. That is why 300 to 500 is described as a sweet spot rather than a minimum. The mold is charged once and belongs to you, so a reorder at higher quantity carries none of it.
Get the credit mechanics into the quotation in writing before the order goes in: the threshold, what it counts against, and which fees are included. Those are the details that get argued about six weeks later.
Why a small order gets turned down
The idea that Chinese factories only want big orders survives because it is half true. Factories do decline small orders, and the reason is rarely the piece count.
What makes an order hard to run is complexity: ten designs, five finishes, four packaging formats and a six-week window. A single design in a single finish at 60 pieces is an ordinary order at a low-MOQ factory and takes an ordinary production slot.
Three habits make a small order easy to accept.
- Hold the first run to one or two finishes.
- Share components across designs where the look allows it.
- Put the whole picture in the first message: design count, quantity per design, finish count, material, stone or pearl type, packaging, target market, and the date you need goods in hand.
TEYING quotes 60 pieces per design as a standard starting point, with brass and 925 sterling silver as the two production materials. The custom jewelry manufacturer page follows a reference from brief through sample to production.
What the first order should leave behind
Four things should survive the run: an approved reference sample, a written specification sheet per SKU, a mold you own, and QC notes from the production. With those in hand, a reorder becomes a quantity conversation instead of a development project, and the 14 to 18 day sampling stage drops out of the schedule entirely.
That is the honest case for a small first order. It is not about spending less. It is about reaching a repeatable specification with the least exposure.
If you have a design count and a target quantity, send them through the TEYING quote form. We will confirm the per-design minimum, the sampling window, and which fees the production order can carry back.
FAQ
I want two plating colors. Is that 60 pieces each?
Yes, unless the split is agreed as part of the project. Each plating color is a separate production run, so an 18K gold version and a rhodium version of the same design mean 60 pieces in each. Put the finish split in the brief so the quotation reflects your actual plan rather than a standard assumption.
How is the design fee credited back?
The design and development fee runs $200 to $800 per design and is credited once the production order passes $2,000. The sample fee, $50 to $150 per sample, is credited against the production order. The mold, $50 to $300 per design, is charged once and is not credited, because you own it and can reuse it.
How fast can a first order ship?
Sampling takes 14 to 18 days and bulk takes 2 to 3 weeks after you approve the sample, which is roughly four to six weeks of factory time before shipping if the sample passes first review. Add transit, quoted by destination, weight and volume. A revision restarts the sampling clock.
What makes a small order hard to schedule?
Complexity, not quantity. Ten designs, five finishes, four packaging formats and a tight deadline is a difficult order at any volume. One design in one finish at 60 pieces is routine. Sharing components across designs and limiting the first run to one or two finishes does more for your schedule than raising the quantity.
What should I keep after the first run?
An approved reference sample, a written specification sheet per SKU, the mold you paid for, and QC notes from the production run. Those four items turn the next order into a quantity conversation, and they remove the 14 to 18 day sampling stage from the calendar completely.